Tag: power sector litigation

Supreme Court Upholds Ruling: Power Generators Must Share Coal Costs Fairly Among All Buyers
Supreme Court

Supreme Court Upholds Ruling: Power Generators Must Share Coal Costs Fairly Among All Buyers

The Supreme Court dismissed appeals against concurrent orders of CERC and APTEL. It upheld that coal linkage for a power plant is allocated to the project as a whole, not to specific PPAs. Consequently, the additional cost from 'Change in Law' events must be apportioned pro-rata among all power procurers based on their energy drawal. Facts Of The Case: GMR Kamalanga Energy Limited (GKEL) set up a power plant and entered into long-term Power Purchase Agreements (PPAs) with three utilities: Haryana, Odisha (GRIDCO), and Bihar. The project was allocated coal from specific linkages and a captive block, intended for the entire plant. When changes in law and a coal supply shortfall increased GKEL's costs, it sought compensation. The Central Electricity Regulatory Commission (CERC) ruled GKEL w...
“Who Pays for Delays in Power Projects? : Supreme Court Explains CERC’s Role in Tariff and Compensation”
Supreme Court

“Who Pays for Delays in Power Projects? : Supreme Court Explains CERC’s Role in Tariff and Compensation”

The Supreme Court held that the Central Electricity Regulatory Commission (CERC) can exercise regulatory powers under Section 79 of the Electricity Act, 2003 to impose compensation for delays, even without specific regulations under Section 178. It clarified that CERC’s orders under Section 79 are appealable to APTEL under Section 111, not through writ petitions unless jurisdictional or constitutional issues arise. The Court emphasized that regulatory gaps can be addressed via Section 79, distinguishing it from legislative rule-making under Section 178. The High Court erred in entertaining the writ petition when an alternative remedy existed. Facts Of The Case: The case involved a dispute between Power Grid Corporation of India Ltd. (PGCIL) and Madhya Pradesh Power Transmission Company L...
Supreme Court Decides “what It Means for Future Agreements” : Lead Partner Liable for Full Payment in Power Project Dispute
Supreme Court

Supreme Court Decides “what It Means for Future Agreements” : Lead Partner Liable for Full Payment in Power Project Dispute

The Supreme Court upheld the doctrine of privity of contract, ruling that Brua Hydrowatt Pvt. Ltd. (BHP) was solely liable for transmission bay costs under its agreement with HP Power Transmission Corporation (HPPTC), despite internal arrangements with third parties. The Court held that non-signatories (Respondent Nos. 2 & 3) could not be bound by the contract, reversing APTEL’s order. The judgment reaffirmed that contractual obligations apply only to parties to the agreement, unless explicitly extended. Facts Of The Case: The dispute arose between HP Power Transmission Corporation Ltd. (HPPTC) and M/s Brua Hydrowatt Pvt. Ltd. (BHP) over the liability for construction and maintenance costs of a 66kV power transmission bay at Urni, Himachal Pradesh. BHP, along with two other power com...