Clarity on Post-Award Interest: Supreme Court Explains When Hyder Consulting Judgment Applies
Supreme Court

Clarity on Post-Award Interest: Supreme Court Explains When Hyder Consulting Judgment Applies

This Supreme Court judgment clarifies that an arbitral award granting a composite interest rate from the cause of action until the date of repayment, based on a contract between the parties, excludes the default application of separate post-award interest under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996. Party autonomy governs, and a decree-holder cannot claim compound interest at the execution stage if it was not stipulated in the contract or awarded by the tribunal, as this would amount to impermissibly modifying the award. Facts Of The Case: The dispute originated from a Memorandum of Understanding (MoU) dated 09.04.2014 between HLV Limited and PBSAMP Projects Pvt. Ltd. for the sale of land in Hyderabad. PBSAMP paid an advance of Rs. 15.5 crores to HLV. After...