Tag: Energy Law

Supreme Court Settles Decade-Long Hydel Power Tariff Battle, Explains Limits of Private PPA Changes
Supreme Court

Supreme Court Settles Decade-Long Hydel Power Tariff Battle, Explains Limits of Private PPA Changes

The Supreme Court affirmed that the electricity tariff and Power Purchase Agreements (PPAs) are not purely private contracts. Under Section 86(1)(b) of the Electricity Act, 2003, they must be reviewed and approved by the State Electricity Regulatory Commission. A generating company and distribution licensee cannot unilaterally set or modify tariffs without the regulatory commission's mandatory approval. Facts Of The Case: The case originated from a dispute over the tariff payable for electricity supplied by M/s. KKK Hydro Power Limited. The company initially established a 3 MW hydro plant under a 2000 Power Purchase Agreement (PPA) with a fixed tariff of ₹2.50/kWh. In 2007, it augmented the project's capacity to 4.90 MW. A new PPA was executed in 2008 for the revised capacity, but it ret...
Supreme Court Backs Discom: Upholds Right to Encash Bank Guarantee in Delayed Solar Project
Supreme Court

Supreme Court Backs Discom: Upholds Right to Encash Bank Guarantee in Delayed Solar Project

The Supreme Court held that the Power Purchase Agreement's explicit terms govern the parties' rights. The encashment of the performance bank guarantee was valid as the developer failed to seek an extension under the contractual mechanism or issue a mandatory Force Majeure notice. Regulatory commissions cannot rewrite the contractual risk allocation or grant remedies outside the agreed framework. Facts Of The Case: The dispute arose from a Power Purchase Agreement (PPA) executed between Chamundeshwari Electricity Supply Company Ltd. (CESC) and Saisudhir Energy Pvt. Ltd. for a 10 MW solar power project. The PPA stipulated that the developer was to achieve the Commercial Operation Date (COD) within 12 months, preceded by fulfilling certain Conditions Precedent within 240 days. A critical pr...
Who Pays for Unpaid Power Bills? Supreme Court Explains ‘Regulatory Asset’ Mess and Orders a Fix
Supreme Court

Who Pays for Unpaid Power Bills? Supreme Court Explains ‘Regulatory Asset’ Mess and Orders a Fix

The Supreme Court ruled that Regulatory Assets, while a valid regulatory tool, must be created only in exceptional circumstances and liquidated in a time-bound manner. It upheld the legal framework under the Electricity Act, 2003, and directed strict adherence to the newly inserted Rule 23 of the Electricity Rules, which mandates a maximum 3% gap in revenue and a 7-year liquidation period for existing assets. The judgment emphasizes the duty of Regulatory Commissions to ensure cost-reflective tariffs and affirms APTEL's power under Section 121 to issue directions against regulatory failure. Facts Of The Case: The case originated from petitions and appeals filed by three private power distribution companies (Discoms) in Delhi—BSES Rajdhani, BSES Yamuna, and Tata Power Delhi—agains...
Supreme Court Late Payment Surcharge Valid:  Coal India’s Levy Ruled as ‘Change in Law’
Supreme Court

Supreme Court Late Payment Surcharge Valid: Coal India’s Levy Ruled as ‘Change in Law’

The Supreme Court upheld the Appellate Tribunal for Electricity's (APTEL) ruling that a Coal India Limited (CIL) notification imposing Evacuation Facility Charges (EFC) constitutes a "change in law" event under the Power Purchase Agreement (PPA). The judgment affirmed that the power generator is entitled to compensation from the notification date with carrying cost at Late Payment Surcharge (LPS) rates on a compounding basis, based on restitutionary principles. The Court clarified that only a substantial question of law is appealable, and the supplementary bill is required only after due adjudication. Facts Of The Case: A Power Purchase Agreement (PPA) was signed on January 28, 2010, between Rajasthan Discoms and Adani Power Rajasthan Ltd. for 1200 MW. On December 19, 2017, Coal India ...