Supreme Court Backs Discom: Upholds Right to Encash Bank Guarantee in Delayed Solar Project
Supreme Court

Supreme Court Backs Discom: Upholds Right to Encash Bank Guarantee in Delayed Solar Project

The Supreme Court held that the Power Purchase Agreement's explicit terms govern the parties' rights. The encashment of the performance bank guarantee was valid as the developer failed to seek an extension under the contractual mechanism or issue a mandatory Force Majeure notice. Regulatory commissions cannot rewrite the contractual risk allocation or grant remedies outside the agreed framework. Facts Of The Case: The dispute arose from a Power Purchase Agreement (PPA) executed between Chamundeshwari Electricity Supply Company Ltd. (CESC) and Saisudhir Energy Pvt. Ltd. for a 10 MW solar power project. The PPA stipulated that the developer was to achieve the Commercial Operation Date (COD) within 12 months, preceded by fulfilling certain Conditions Precedent within 240 days. A critical pr...
Supreme Court Rules :Landowners Can’t Get Uniform Compensation for Power Lines
Supreme Court

Supreme Court Rules :Landowners Can’t Get Uniform Compensation for Power Lines

The Supreme Court set aside the High Court's judgment for failing to properly assess compensation under the Indian Telegraph Act, 1885. It emphasized that compensation must be determined based on location-specific evidence and remanded the cases. The Court also highlighted the absence of a statutory appeal mechanism against orders of the District Judge and referred the issue to the Law Commission for examination. Facts Of The Case: A power transmission project titled "400 KV Jhajjar Power Transmission System-PPP-1" was initiated by HVPNL in Haryana. Jhajjar KT Transco Private Limited (JKTPL) was awarded the project, which sub-contracted the erection work to Kalpataru Power Transmission Ltd. The 100 km-long transmission line passed through land in four districts, including Sonepat and Jha...