Supreme Court Settles Decade-Long Hydel Power Tariff Battle, Explains Limits of Private PPA Changes
Supreme Court

Supreme Court Settles Decade-Long Hydel Power Tariff Battle, Explains Limits of Private PPA Changes

The Supreme Court affirmed that the electricity tariff and Power Purchase Agreements (PPAs) are not purely private contracts. Under Section 86(1)(b) of the Electricity Act, 2003, they must be reviewed and approved by the State Electricity Regulatory Commission. A generating company and distribution licensee cannot unilaterally set or modify tariffs without the regulatory commission's mandatory approval. Facts Of The Case: The case originated from a dispute over the tariff payable for electricity supplied by M/s. KKK Hydro Power Limited. The company initially established a 3 MW hydro plant under a 2000 Power Purchase Agreement (PPA) with a fixed tariff of ₹2.50/kWh. In 2007, it augmented the project's capacity to 4.90 MW. A new PPA was executed in 2008 for the revised capacity, but it ret...
Supreme Court Clarifies Jurisdiction of Electricity Regulators in Franchisee Disputes
Supreme Court

Supreme Court Clarifies Jurisdiction of Electricity Regulators in Franchisee Disputes

The Supreme Court ruled that Electricity Regulatory Commissions (ERCs) lack jurisdiction to entertain petitions solely based on public interest under the Electricity Act, 2003. It held that franchisees, as agents of distribution licensees, are not directly regulated by ERCs, and investigations under Section 128 must target licensees, not franchisees. The Court emphasized that ERCs cannot micromanage franchisee agreements, as their regulatory oversight is limited to licensees. The judgment clarified that contractual disputes between licensees and franchisees fall outside ERCs' adjudicatory scope under Section 86(1)(f). The appeal was allowed, setting aside APTEL's order. Facts Of The Case: The case involved a dispute between Torrent Power Limited (appellant) and the Uttar Pradesh Elec...