Tag: Civil Appeal No. 12883 of 2024

Supreme Court Clarifies When Electricity Contracts Beat Regulatory Caps
Supreme Court

Supreme Court Clarifies When Electricity Contracts Beat Regulatory Caps

The Supreme Court ruled that Note 3 of Regulation 55 of the CERC Regulations, 2019, which caps free power supply to states at 13%, is only for tariff calculation and does not override contractual obligations under the Implementation Agreement. The Court held that writ jurisdiction was inappropriate, as disputes involving regulatory interpretation must first be addressed by the specialized CERC. The judgment reaffirms that contractual rights remain enforceable unless expressly prohibited by law. Facts Of The Case: The case involves a dispute between the State of Himachal Pradesh and JSW Hydro Energy Limited over the supply of free power from a hydroelectric project. In 1993, the state allotted the Karcham Wangtoo Hydroelectric Project to a predecessor company of JSW Hydro under a Memorand...