Tag: Breach of Contract

Supreme Court Backs Discom: Upholds Right to Encash Bank Guarantee in Delayed Solar Project
Supreme Court

Supreme Court Backs Discom: Upholds Right to Encash Bank Guarantee in Delayed Solar Project

The Supreme Court held that the Power Purchase Agreement's explicit terms govern the parties' rights. The encashment of the performance bank guarantee was valid as the developer failed to seek an extension under the contractual mechanism or issue a mandatory Force Majeure notice. Regulatory commissions cannot rewrite the contractual risk allocation or grant remedies outside the agreed framework. Facts Of The Case: The dispute arose from a Power Purchase Agreement (PPA) executed between Chamundeshwari Electricity Supply Company Ltd. (CESC) and Saisudhir Energy Pvt. Ltd. for a 10 MW solar power project. The PPA stipulated that the developer was to achieve the Commercial Operation Date (COD) within 12 months, preceded by fulfilling certain Conditions Precedent within 240 days. A critical pr...
Supreme Court Denies Specific Performance Over Tainted Agreement: Readiness to Pay Not Enough
Supreme Court

Supreme Court Denies Specific Performance Over Tainted Agreement: Readiness to Pay Not Enough

The Supreme Court upheld the denial of specific performance, ruling that a material alteration in the sale agreement—visibly apparent from the use of different ink for a property's description—vitiated the contract. Courts are not always obligated to seek expert opinion under Section 73 of the Evidence Act when such an alteration is plainly discernible upon a mere perusal of the document itself. Facts Of The Case: The plaintiff-appellant, Syed Basheer Ahmed, entered into a sale agreement dated July 15, 1984, with the first defendant for the purchase of two properties: Item No. 1 (owned by the first defendant) and Item No. 2 (owned by a third party). The total agreed consideration was Rs. 56,000/-, with an advance of Rs. 1,000/- paid. The agreement stipulated that the sale deed was to be ...
Promises Must Be Kept: Supreme Court Protects Industry from Unexpected Tariff Hikes by State Board
Supreme Court

Promises Must Be Kept: Supreme Court Protects Industry from Unexpected Tariff Hikes by State Board

The Supreme Court held that the electricity board was estopped from resiling from its contractual obligation to provide a concessional tariff after having sanctioned, agreed, and partially implemented it. The board's unilateral withdrawal of the concession after over two years was deemed arbitrary, illegal, and unsustainable in law. Facts Of The Case: The appellant, an existing industrial unit with a Low Tension (LT) power connection, underwent significant expansion by installing a large induction furnace, which necessitated a High Tension (HT) or bulk power supply. It applied for this new connection in 1998. The respondent electricity board, after inspection, sanctioned the HT connection via a memo that explicitly stipulated the appellant’s eligibility for a 25% concessional tarif...
Supreme Court Rules on Loan Disguised as Property Deal, Protects Homeowner from Forced Sale
Supreme Court

Supreme Court Rules on Loan Disguised as Property Deal, Protects Homeowner from Forced Sale

The Supreme Court held that the plaintiff failed to prove the existence of a valid sale agreement, a prerequisite for specific performance under Man Kaur v. Hartar Singh Sangha. The burden of proof was not discharged as the sole evidence was self-serving and key witnesses were not examined. The High Court's reversal of concurrent factual findings was erroneous. Facts Of The Case: The respondents (original plaintiffs) filed a suit for specific performance of an alleged sale agreement dated 12.02.1999, claiming the appellant (defendant) had agreed to sell his house for Rs. 70,000. They asserted having paid Rs. 55,000 as advance and taken possession, subsequently renting the property back to the appellant. The appellant contested the suit, denying any agreement to sell. His defense was that...
Landmark Judgment: Supreme Court Orders Eviction of Bidder Who Failed to Pay for 3 Decades
Supreme Court

Landmark Judgment: Supreme Court Orders Eviction of Bidder Who Failed to Pay for 3 Decades

The Supreme Court upheld the Tamil Nadu Housing Board's cancellation of allotment due to the respondent's chronic default in payment over decades. The Court emphasized that public property must be managed transparently and in the public interest, rejecting the respondent's claims. It ruled that prolonged non-payment justified eviction, denying further indulgence and ordering possession to be surrendered within four months. The judgment reinforced that contractual obligations must be honored and that courts cannot indefinitely protect defaulters at the cost of public welfare. Facts Of The Case: In 1986, the Tamil Nadu Housing Board auctioned a prime commercial plot in Chennai, with S. Ganesan emerging as the highest bidder at ₹4,78,921. Despite the Board's acceptance of his bid, Gan...
Civil Dispute, Not Crime: SC Quashes FIR Against Businessman Calls It a Contract Issue
Supreme Court

Civil Dispute, Not Crime: SC Quashes FIR Against Businessman Calls It a Contract Issue

The Supreme Court quashed an FIR alleging cheating (Section 420 IPC) and criminal breach of trust (Section 406 IPC), holding that unpaid export transactions constituted a civil dispute, not a criminal offense. The Court emphasized that mere breach of contract, without dishonest intent at inception, cannot attract criminal liability. It ruled that the exporter (M/s. Oswal Overseas), not the accused, was the entrusted party, and the complainant failed to establish fraudulent inducement or entrustment under Sections 405/415 IPC. The judgment reaffirmed that criminal proceedings cannot remedy purely contractual disputes. Facts Of The Case: The case involved a business dispute between Ashok Kumar Jain (appellant), director of a Sri Lankan export-import firm, and a Gujarat-based textile trader...